Sanwo-Olu says Lagos rail initiatives will price over N100 billion

0 5

The Federal Government has given a timeline for the completion of the Apapa-Oshodi-Ojota-Oworonsoki expressway challenge.

The authorities mentioned the reconstruction/rehabilitation of the expressway which was inaugurated by President Muhammadu Buhari in November 2018, to resolve the Apapa visitors gridlock, shall be accomplished inside 9 to 10 months.

This disclosure was made by the Federal Controller of Works in Lagos, Mr Olukayode Popoola, throughout a joint inspection with the Nigerian Ports Authority (NPA) on Saturday, April 17, 2021.

He assured that part one of many challenge can be accomplished inside 3 weeks and thereafter opened to be used.

Popoola mentioned that the rehabilitation works, which had been divided into 4 sections to ease port congestion and gridlock on the Apapa axis, have part one which spans from Liverpool Round by Creek Road to Beachland close to Sunrise and is about 10 km, whereas part two is 8.4 km and spans from Beachland to Cele Bus Stop.

Briefing the press after the inspection that additionally had in attendance the NPA Managing Director, Hadiza Usman, and the Hitech Construction Company, the subcontractor dealing with the challenge on behalf of the Dangote Group, Popoola mentioned that gray areas resembling accessibility as a result of vehicles infringing on development zone and disagreements on the tempo of development had been resolved.

What the Federal Controller of Works in Lagos is saying

Popoola mentioned that the inspection gave the NPA staff the chance to see for themselves that the contractor had been working progressively.

He mentioned, “And this part that we’re is the top of part one which now we have accomplished. We will full the remaining portion throughout the subsequent three weeks, particularly the asphalt work.

So inside that three weeks, the excellent works shall be accomplished absolutely after which the part one shall be made out there to the motorists.

We (FMW) additionally complained concerning the vehicles which might be infiltrating the highway whereas we’re working. We have advised them (NPA) that we can’t permit vehicles to flock onto the part the place we’re working as a result of they may disturb the contractor.

So the vehicles will now be monitored and managed absolutely. Both the NPA safety, the Nigerian Police, LASTMA after which the contractor’s consultant will type a synergy to work out how they are going to be controlling the vehicles that enter into the port highway henceforth,’’ Popoola mentioned.

He mentioned the contractor is anticipated to maneuver to web site to start out the development works on part two of the challenge based mostly on settlement including that work on sections three and 4 had reached a complicated stage, with over 70% completion reached cumulatively.

Popoola mentioned that your entire challenge can be accomplished and handed over throughout the subsequent 9 to 10 months, together with part two which had simply been awarded.

The NPA Managing Director mentioned that agreements had been reached on timelines for development works so as to not disrupt port operations with resolutions that the contractor labored in the course of the weekends and on public holidays to ease congestion.

She mentioned it was resolved {that a} hall can be opened for vehicles motion along with palliative works on some roads and one other inspection in three weeks on part one.

The contract was awarded to AG Dangote Construction Company Ltd at the price of N73bn below the Tax Credit Scheme of the Federal Government.

What it’s best to know

  • It could be recalled that the Federal Government had earlier within the 12 months mentioned that the primary part of the Apapa-Oshodi-Ojota-Oworonshoki challenge, which has confronted a number of delays, can be delivered in April 2021.
  • The authorities mentioned that sections one, three and 4 of the challenge which was awarded to AG Dangote Construction Company Ltd at the price of N73bn below the Tax Credit Scheme of the Federal Government, had been nearly prepared and can be accomplished in April.
  • They had additionally mentioned that part two of the challenge which spans from Beach Land bus cease space to Cele Bus Stop which was not too long ago awarded would even be accomplished in December 2021.